Northern Education Trust had designated four of their school’s gas plant as inefficient and unable to cope effectively for the coming winter period and would require replacing during the summer school break 2019.

Following a successful tender process NET awarded JH Mechanical Services all four projects, confident in our ability to deliver all four projects in good time for the schools return, estimated works at £100K.

The works are now all complete, in time for the start of the new school term.

 

Kelly Officer, Estates Officer Northern Education Trust said: “I would like to express my thanks to Liam and all of the engineers concerning all four of our sites for their hard work and professionalism throughout these projects.

I understand there were some challenging sites in which to work therefore I especially appreciate the teams effort and understanding.

It was lovely to work with JH Mechanical Services.”

 

Location: Abbey Park Academy, Halifax and Ryecroft Primary Academy, Bradford

The Project:

In both of these schools, three atmospheric inefficient gas boilers were removed along with all associated pipework and flue systems. Three high efficiency skid mounted condensing boilers with new associated pipework and flue systems were installed including installation of a magnetic water filter system to maintain water quality, ensuring efficiency for years to come. Also, a gas detection system was installed providing confidence in gas safety for the client.

Location: Frederick Nattrass Primary School, Stockton

The Project:

An inefficient and problematic gas water heater was removed along with all associated pipework and flue system. A fully condensing, gas fired, stainless steel, floor standing water heater and direct storage vessel with new associated pipework, pumps and flue system were installed.

Frederick Nattrass Primary School

 

Location: Oak Tree Academy, Stockton

The Project:

Four atmospheric inefficient gas boilers were removed along with all associated pipework and flue systems. Four high efficiency skid mounted condensing boilers with new associated pipework and bespoke flue system were installed including installation of a magnetic water filter system to maintain water quality, ensuring efficiency for years to come as well as integration to the existing building management system.

Oak Tree Academy